Sitowise is implementing a battery energy storage solution (BESS project) for Imatran Seudun Sähkö, connected to the distribution grid. The scope includes principal and architectural design, fire safety engineering, structural engineering, electrical and data transmission cabling design, geotechnical engineering, as well as construction management and site supervision. 

The work includes the preparation of design documentation, including design meetings, supervision during construction and safety coordinator duties, as well as supplier support during tendering and commissioning.

The implementation emphasises the coordination of designs, the provision of documents required for the permitting process, and the supervision of safety and quality on site. Sitowise’s operating model enables the project to progress smoothly from design to commissioning and ensures overall project management, from distribution grid connections through to technical site supervision.

  • Customer:
    Imatran Seudun Sähkö
  • Date of implementation:
    2025